Which estimation technique uses a relationship between 2 variables to determine a unit duration? For example, if it took 3 days to manufacture 5 computers, it would take 6 days to manufacture 10 computers.
Expert Judgment
Reserve Analysis
Parametric Estimating
Three Point Estimates
Analogous Estimating
The Estimate Activity Duration which best describes this method is Parametric Estimating.